Hi Gurus,

I have a requirement in Feb 20th and have my planning time fence is April 14th .

We had created manually receipt element created in  May 10th. When i run Planning run a new receipt element is created on April 14th.

Can any one please suggest how i can i stop system to create new receipt element on April14th and ask the system to look forward to May 10th ?

 

It will be really helpful if any one can suggest.

 

Thanks a lot

 