Dear All,
When the user tries to create the PR on the activity 1280 , Budget Exceeded Error is displayed but we have enough Budget
The detailed error Message is Payment Budget for WBS Element X123.03 on Network Activity 1280 been exceeded by X Amount.
Kindly help.
Thanks in Advance.
Regards,
Shareeq